South Veterans Parkway
The South Veterans Parkway project is a partnership with the South Dakota Department of Transportation (SDDOT) and the City of Sioux Falls.
Friday, September 27, 2024 Construction Updates
- Lane closures on Minnesota Avenue are no longer in place. All lanes of Minnesota Avenue are now open.
- Work on Western Avenue, south of 95th Street, is progressing with landscaping, asphalt, and cleanup.
- The contractor is installing the colored concrete on Veterans Parkway as well as working on lighting and landscaping.
- The roundabout construction at Western Avenue and 95th Street is complete. This intersection is now open and available for use. The south leg of the roundabout is closed until project completion in late 2024.
Current Traffic Impacts
Western Avenue Closure:
- Western Avenue from the intersection of 95th Street to 271st Street (County Road 106) is closed.
- The intersection at 271st Street is open to traffic.
Click or tap on the icons to learn more about each segment of the new South Veterans Parkway.
What to Expect During Construction
- Construction work Monday - Saturday
- Construction materials and equipment
- Trucks hauling materials
- Noise during construction work hours
- Dust management
About the Project
When connected to the northern segment of Veterans Parkway, the additional nine miles of roadway for South Veterans Parkway will support a regional arterial road network around southeast Sioux Falls. This project — the final stage in connecting Interstate 29 with Interstate 90 — will accommodate growing transportation needs across the corridor and help prepare the greater Sioux Falls area for continued vibrant growth and development.
The first road segment from Western Avenue to Cliff Avenue is currently under construction. Design for the other three segments is simultaneously underway, beginning with design for segment two of the project, which runs from I-29 to Western Avenue. The three additional segments for South Veterans Parkway will be constructed over the following years until the corridor is completed in 2027. Learn more about each segment.
- 2021 - Environmental Planning and Design
- 2022 - Design and Real Estate Acquisition
- 2023 to 2024 - Segment 1: Western Avenue to Cliff Avenue (we are here)
- 2024 to 2025 - Segment 2: I-29 to Western Avenue
- 2025 to 2026 - Segment 3: Cliff Avenue to Sycamore Avenue
- 2026 to 2027 - Segment 4: Sycamore Avenue to 57th Street
Project Benefits
- Increased traffic flow
- Corridor connectivity
- Accommodate public and private investment